Case Study · Outdoor Sports Court Development

Shaded Acrylic Multi-Sport Court for a School in Dubai

Dubai, UAE | 2024

An exposed, paved courtyard at an educational campus in Dubai, rebuilt as a fully shaded, all-weather acrylic court for netball and basketball. Smart Field Sports delivered the complete scope, from site clearance and a reinforced concrete base to tensile shade sails, a cushioned acrylic surface and game lines, in about five weeks of the summer holidays.

Project overview

The school had an open courtyard between two of its buildings, finished in interlock paving and planted with palm trees behind a timber fence. It sat in full sun and could not be used as a marked sports court.

The requirement was a covered playing surface for netball and basketball, built while the campus was closed for the summer so that it would be ready for the new academic term.

Smart Field Sports took on the work as a single contractor. Our team removed the existing landscaping and paving, built a compacted road-base and a reinforced concrete slab, set kerbstones around the perimeter, installed tensile shade sails over the full playing area and finished the court with a multi-layer acrylic sports surface and line marking.

The school now has a shaded, all-weather court for PE lessons and sport, in a space that was previously unused.

Project objectives

What did the school need from the new court?

Turn unused space into a sports court

Convert a paved courtyard into a marked court that supports netball and basketball for PE and school sport.

Protect players from sun and heat

Cover the whole playing area with tensile shade, so the court stays usable in UAE conditions for more of the day and the year.

Provide a safer, more comfortable surface

Use a textured acrylic system with cushion layers instead of hard paving underfoot.

Build on a stable, long-life base

Replace the paving with a compacted road-base and a reinforced concrete slab that gives the acrylic system a sound, level substrate.

Finish within the school holidays

Complete the full scope while the campus was closed, so the court was ready for the new term without disrupting lessons.

Challenges and how we solved them

A fixed deadline: the start of the new term

The challenge

Every trade had to fit inside the summer holiday window.

Our solution

We sequenced the work so that trades overlapped where the process allowed. The tensile shade was installed while the concrete slab was curing, so no time was lost waiting before the surfacing could start.

Existing landscaping and paving to remove

The challenge

The courtyard contained palm trees, a timber fence and interlock paving that all had to come out before any new construction.

Our solution

The site was cleared mechanically, the interlock and fence were removed, and all material and debris were carted away. The ground was then excavated and levelled ready for the new sub-base.

Peak summer heat in July and August

The challenge

Surfacing outdoors in the hottest months exposes both the crew and the coatings to direct sun.

Our solution

Because the shade sails were installed before surfacing began, the acrylic layers were applied under cover. Each layer was left to dry for the specified interval before the next was applied.

Working beside building entrances on a school campus

The challenge

The court sits between buildings, next to entrances used by staff during the holidays.

Our solution

The work zone was segregated with barrier tape and traffic cones throughout, and kept separate from pedestrian routes.

Complete scope of works

What did Smart Field Sports deliver on this project?

  • Site assessmentInspection and photographic survey of the existing courtyard before work started.
  • Site clearanceRemoval of palm trees, the timber fence and the existing interlock paving, with all debris carted away.
  • Excavation and sub-baseExcavation of existing soil up to 250 mm, then a 150 mm road-base aggregate layer, levelled and compacted with a heavy roller.
  • Kerbstone perimeterHeel kerbstones fixed on a PCC 1:4:8 concrete bed over polythene sheet, then backfilled.
  • Reinforced concrete base100 mm RCC slab with steel mesh reinforcement, using SRC 300 (or equivalent) ready-mix concrete, with shuttering where required.
  • Levelling and curingCement grouting (CM 1:5) over the finished concrete to bring it to level, followed by water curing.
  • Tensile shade sailsWall plates anchored to the existing concrete walls, stainless-steel wire ropes, and UV-stabilised HDPE shade fabric tensioned with webbing belts and stainless-steel D-shackles.
  • Acrylic sports surfacePrimer, a base layer filled with silica sand, two types of cushion layer, a sealer, two textured surface coats and a UV-protective top coat.
  • Line markingCourt markings for netball and basketball in acrylic line paint.
  • Site safetySegregation of the work zone with barrier tape and cones throughout the works.

Step-by-step project execution

How was the court built? Twelve stages, in the order they happened on site.

  1. Existing paved school courtyard with palm trees and timber fencing before the court project
    The courtyard at the site assessment stage.

    Stage 01

    Existing site and assessment

    Before work started, we surveyed the courtyard and recorded its condition: interlock paving, mature palm trees, a timber fence and no sports markings.

    Purpose
    To confirm what had to be removed and to plan the construction sequence around the school calendar.
    Materials and equipment
    Site survey and photographic record.
    Workmanship
    The survey was used to plan the clearance and the order of works.
  2. Courtyard after removal of palm trees, fence and interlock paving, with lifted pavers stacked at the side
    Site cleared: palm trees, fence and paving removed.

    Stage 02

    Site clearance

    The palm trees, timber fence and interlock paving were removed and the material was carted away from site.

    Purpose
    To clear the full footprint down to the existing ground before excavation.
    Materials and equipment
    Mechanical plant and hand tools; removal and disposal of debris.
    Workmanship
    Clearance stopped at the line of the surrounding paving that was to remain, so adjacent areas were left intact.
  3. Ride-on roller and plate compactor compacting the road-base sub-base for the new court
    Road-base sub-base compacted with a ride-on roller.

    Stage 03

    Excavation and road-base compaction

    Existing soil was excavated up to 250 mm. A 150 mm layer of road-base aggregate was then spread, levelled and compacted.

    Purpose
    A well-compacted sub-base gives the concrete slab uniform support and limits later settlement.
    Materials and equipment
    Road-base aggregate; ride-on roller and plate compactor.
    Workmanship
    Levels were corrected during compaction so the slab could be laid to a consistent thickness.
  4. Heel kerbstones being set along the court perimeter on a concrete bed
    Heel kerbstones set along the court perimeter.

    Stage 04

    Kerbstone perimeter

    Heel kerbstones were set on a PCC 1:4:8 bed over polythene sheet around the boundary, and the soil was backfilled behind them.

    Purpose
    Kerbs define the court edge, retain the base and protect the edge of the finished surface.
    Materials and equipment
    Heel kerbstones, PCC 1:4:8 bedding, polythene sheet.
    Workmanship
    The kerbs form the edge against which the concrete slab was later poured.
  5. Crew placing and screeding a reinforced concrete slab over steel mesh, with the concrete pump boom above
    The 100 mm RCC slab being placed and screeded over steel mesh.

    Stage 05

    Reinforced concrete slab

    A 100 mm reinforced concrete slab was placed over steel mesh, pumped into position and screeded to level.

    Purpose
    The slab is the structural base for the acrylic system, which needs a sound, level and stable substrate.
    Materials and equipment
    Steel mesh reinforcement; SRC 300 (or equivalent) ready-mix concrete; concrete pump; screed boards.
    Workmanship
    Concrete was screeded with straight-edge boards as it was placed, working across the mesh.
  6. Cured concrete base slab ready for the acrylic sports surface
    The cured concrete base, ready for the acrylic system.

    Stage 06

    Levelling and curing

    After the pour, the surface was grouted with a 1:5 cement mortar to bring it to level, then water-cured.

    Purpose
    Proper curing helps the concrete reach its intended strength and reduces the risk of surface cracking.
    Materials and equipment
    Cement mortar CM 1:5; water curing.
    Workmanship
    The slab was left to cure before any coating work began; the shade installation went ahead during this period.
  7. Teal tensile shade sails installed over the concrete court base between two buildings
    Tensile shade sails installed while the slab cured.

    Stage 07

    Tensile shade sails

    Wall plates were anchored to the existing concrete walls, stainless-steel wire ropes were fixed between them, and the HDPE shade fabric was tensioned onto the system.

    Purpose
    The sails cover the whole playing area, protecting players from direct sun and allowing the surfacing to be applied under shade.
    Materials and equipment
    Wall plates and anchor bolts; stainless-steel wire rope; UV-stabilised, knitted HDPE shade fabric; webbing belts; stainless-steel D-shackles.
    Workmanship
    Each sail was tensioned evenly so the fabric sits taut, without loose areas that flap or collect dust.
  8. Installer rolling acrylic primer onto the prepared concrete court base
    Primer rolled onto the prepared slab.

    Stage 08

    Primer coat

    The acrylic system started with a primer, rolled onto the prepared concrete.

    Purpose
    The primer seals the concrete and gives the following acrylic layers a sound bond.
    Materials and equipment
    Acrylic primer, applied by roller.
    Workmanship
    The slab surface was cleaned before priming; the primer was rolled out in even passes.
  9. Acrylic base layer applied across the court under the shade sails
    Base layer applied under the completed shade sails.

    Stage 09

    Base layer with silica sand

    A base layer of acrylic mixed with silica sand was applied in two passes over the primer.

    Purpose
    This layer smooths minor surface variations and builds a uniform foundation for the cushion layers.
    Materials and equipment
    Acrylic base material, silica sand, water.
    Workmanship
    Each pass was left to dry for the specified interval before the next coat.
  10. Acrylic cushion and sealer layers in progress on the shaded court
    Cushion and sealer layers in progress.

    Stage 10

    Cushion and sealer layers

    Two types of cushion layer were applied, followed by a sealer coat mixed with silica sand.

    Purpose
    The cushion layers add some give underfoot compared with bare concrete; the sealer closes the cushion layers ready for the surface coats.
    Materials and equipment
    Acrylic cushion materials, sealer, silica sand.
    Workmanship
    Layers were applied in the specified sequence and quantities, under the completed shade sails.
  11. Textured acrylic play coat applied across the shaded court
    Textured play coats and UV-protective top coat.

    Stage 11

    Textured play coats and UV top coat

    Two textured surface coats were applied, followed by a UV-protective top coat in the playing-area and surround colours.

    Purpose
    The textured finish provides grip, and the top coat protects the colour from sun exposure.
    Materials and equipment
    Acrylic surface coats with silica sand; UV-protective top coat.
    Workmanship
    Colours were applied in sequence, with the playing area and the surround laid out separately.
  12. Finished acrylic court with white netball and basketball lines and a blue surround
    Netball and basketball lines on the finished surface.

    Stage 12

    Line marking

    Netball and basketball lines were set out and painted onto the finished surface.

    Purpose
    Accurate markings let the court be used for both sports.
    Materials and equipment
    Acrylic line-marking paint.
    Workmanship
    Lines were set out to the court layout before painting.

Materials and technical specifications

What is the court made of, from the ground up?

Specified construction for the shaded acrylic court
Element Specification
Site preparation Removal of palm trees, timber fence and interlock paving; debris carted away
Excavation Existing soil excavated up to 250 mm
Sub-base 150 mm road-base aggregate, compacted with heavy roller
Edge restraint Heel kerbstones on PCC 1:4:8 bed over polythene sheet
Concrete base 100 mm RCC slab with steel mesh reinforcement; SRC 300 or equivalent ready-mix
Surface levelling Cement grouting CM 1:5; water curing
Acrylic system Cast-in-place, multi-layer acrylic sports surface
Acrylic build-up Primer · base layer with silica sand (2 passes) · cushion layers (2 types) · sealer · textured surface coat (2 passes) · UV-protective top coat
Line marking Acrylic line paint; netball and basketball
Shade fabric UV-stabilised HDPE, monofilament and tape construction, lock-stitch knit
Shade fixings Wall plates with anchor bolts, stainless-steel wire rope, webbing belts, stainless-steel D-shackles

Values above are the specified build-up for this project. Smart Field Sports can provide product data for each layer on request.

Quality assurance and safety

  • Staged inspections Each stage was checked before the next began: sub-base levels before the slab, the cured slab before priming, and each acrylic layer before the next was applied.
  • Drying and curing intervals Concrete was water-cured, and each acrylic layer was left to dry for the specified interval before the next coat.
  • Even shade tensioning Sails were tensioned evenly on the wire-rope system so the fabric sits taut.
  • Line set-out Court lines were set out to the layout before painting.
  • Segregated work zone Barrier tape and cones kept the work area separate from pedestrian routes beside the building entrances.

These checks matter because faults in the base show through the finished surface. A well-compacted sub-base and a properly cured slab are what keep an acrylic court level and free of cracks, and correct drying times between layers help the system bond as one.

Court corner with barrier tape and a traffic cone segregating the work zone
Barrier tape and cones kept the work zone segregated.

Before and after

Finished shaded acrylic multi-sport court at a Dubai school, with teal tensile shade sails over a red court with blue surround and white lines After: August 2024
School courtyard before construction, with interlock paving, palm trees and a timber fence Before: May 2024
The same view, before and after: the paved courtyard became a fully shaded multi-sport court. Interlock paving, palm trees and a timber fence. A shaded, marked acrylic court for netball and basketball.

Completed project gallery

Results and benefits

A new court in unused space

A paved courtyard that had no sports use is now a marked court for netball and basketball.

Full shade cover

The tensile sails cover the whole playing area, so the court is shaded throughout the day.

A cushioned, textured surface

Players move on a textured acrylic system with cushion layers instead of hard paving.

All-weather outdoor use

The acrylic surface on a reinforced concrete base is built for year-round outdoor use in the UAE climate.

Delivered in the holidays

The full scope was completed in about five weeks, before the new term began.

Why Smart Field Sports

One contractor, full scope

Civil works, kerbs, concrete, shade sails and acrylic surfacing were delivered by one team, so there were no hand-overs between separate contractors.

Planned around the school calendar

We programme school projects into holiday windows and sequence trades to protect the deadline.

Specification-led installation

Each layer is applied to a written specification, with set materials, quantities and drying times.

Dedicated installation team

Installation is carried out by our dedicated, experienced installation team.

Experience with schools across the UAE

Smart Field Sports has supplied and installed sports facilities for more than 100 schools across the UAE.

Frequently asked questions

An acrylic sports court is a hard court finished with layers of acrylic coating applied on site over a concrete or asphalt base. The layers are mixed with silica sand to create a textured, slip-resistant finish, and can include cushion layers for added comfort underfoot.

This court is marked for netball and basketball. Acrylic surfaces are also widely used for tennis, volleyball and general PE, with the markings and equipment chosen to suit each sport.

The acrylic layers are thin, so they follow whatever is underneath. A compacted sub-base and a reinforced concrete slab give a level, stable substrate that resists settlement and cracking, which keeps the playing surface flat.

Cushion layers add a degree of give compared with bare concrete, which makes the court more comfortable to play on. They sit between the base layer and the sealer in the acrylic build-up.

Shade sails protect players from direct sun, so the court can be used for more of the day and more of the year. On this project the shade also went up before surfacing, so the acrylic layers were applied under cover.

This project took about five weeks from site clearance to line marking. The time for any project depends on the scope, the site conditions, access and the curing time the concrete and coatings need.

Yes. This court was built while the campus was closed for the summer. Planning early lets us confirm the scope, order materials and programme the work to finish before the new term.

Keep the surface clean by regular sweeping and occasional washing with water, keep sharp objects and heavy wheeled loads off it, and inspect it periodically. Worn top coats can be renewed when needed. Smart Field Sports can advise on a maintenance routine for your court.

Conclusion

The school needed a covered sports court in a space that was exposed, paved and unused, and it had to be ready for the new term. Smart Field Sports delivered the full solution as one contractor: clearance, a compacted sub-base and reinforced concrete slab, a kerbstone edge, tensile shade over the whole court and a multi-layer acrylic surface marked for netball and basketball, in about five weeks of the summer holidays. The result is a shaded, all-weather court that the school can use for PE and sport throughout the year.

Get in touch

Planning a sports facility project in the UAE?

Smart Field Sports LLC provides sports facility design coordination, material supply and installation for schools, sports clubs, institutions and recreational facilities across the UAE. Tell us about your site and we will help you plan the right solution.